In a special and demanding environment, we undertook the erection and placement of beams weighing 95 tons for the construction of a bridge. The challenge was to lift and place the beams as each one weighed 95 tonnes. To complete this demanding mission, we used a combination of four different cranes.
One of the cranes used was the LIEBHERR LTM 1500-8.1. This telescopic crane has an impressive lifting capacity of up to 500 tonnes. Another crane used was the LIEBHERR LTM1225. This telescopic crane also has an impressive lifting capacity of up to 225 tonnes. In addition, two more cranes with a lifting capacity of 90 tons were used in this project.
Thanks to the correct and intelligent planning of the project, we managed to complete the erection and placement of the beams earlier than expected. This highlights the skill and professionalism of our team.